Interconnection Queue Maps for Major U.S. ISO's & Utilities

LandGate’s interconnection maps show, step by step, how new generators and large loads such as data centers connect to the grid in all seven U.S. ISOs (PJM, MISO, ERCOT, SPP, CAISO, NYISO, ISO-NE) and seven major utilities, including Duke Energy, FPL and PacifiCorp. Click any step to see what happens, what it costs, how long it takes and what can stop a project. Updated monthly as rules change.

Select a grid region

Point at a region to preview it. Select it to open its interconnection guide.

Grid Operators (ISOs and RTOs)

Regional operators that run organized interconnection queues under FERC rules.

PJM

PJM Interconnection

Covers 13 states and Washington, DC​

ERCOT

Electric Reliability Council of Texas

Covers most of Texas​

ISO-NE

ISO New England

Covers CT, ME, MA, NH, RI, and VT

CAISO

California ISO

Covers most of California, part of Nevada

SPP

Southwest Power Pool

Covers 14 central states

NYISO

New York ISO

Covers New York State​

MISO

Midcontinent ISO

15 states and Manitoba

ISO/RTO
Generator Process
Large load path
Large load threshold
Latest rule change
MISO
Annual cycles with 3 study phases and 2 decision points
Through the transmission owner; no dedicated load queue yet
Rules pending
Large-load reliability rules filed Aug 28, 2026 (pending at FERC)
PJM
Cycle process with 3 study phases and 3 decision points
Through the utility; no PJM load queue
50 MW+
FERC accepted large-load definition, Oct 9, 2026
ERCOT
No cluster: each project moves on its own; 18–30 months typical
ERCOT batch study (Batch Zero)
75 MW+
PUCT large-load rule effective Oct 8, 2026
SPP
One annual cluster under the Consolidated Planning Process, with one decision point
HILL framework, with a curtailable bridge service
50 MW+ above 69 kV; 10 MW+ at 69 kV and below
CHILLS curtailable service effective Jul 1, 2026
CAISO
Annual cluster; projects are scored and only top scorers are studied
Through the utility under CPUC rules; no CAISO load queue
Set by the utility
FERC accepted IPE 5.0 compliance filing, Sep 30, 2026
NYISO
Two-phase cluster study
NYISO runs the study; the utility signs the agreement
Over 10 MW at 115 kV+
Large-load reform filing targeted Nov 16, 2026 (pending)
ISO-NE
Annual cluster with flat entry deposits
Proposed serial study process
50 MW+ above 60 kV (proposed)
First regular cluster window opened Oct 5, 2026

Non-RTO utility regions

Utilities that run their own FERC cluster process and large-load rules.

APS

Arizona Public Service

Covers Arizona​

FPL

Florida Power and Light

Covers Florida

SOCO

Southern Company

Georgia, Mississippi, Alabama

PacifiCorp

Pacific Power & Rocky Mountain Power

YT, WY, ID, OR, WA, and CA

PSCo (Xcel Energy)

Public Service Company of Colorado

Covers Colorado

Duke Energy

DEC and DEP

North and South Carolina

PNM

Public Service Company of New Mexico

Central and Northern NM

Utility
Generator Process
Large load path
Large load threshold
Latest rule change
SOCO
Annual cluster; window opens Feb 15, then one shared cluster study and a serial facilities study
Service contract under state rules (GA, AL or MS), then Southern’s large-load integration checklist and testing
Above 40 kV, typically 50 MW+; Georgia PSC review over 100 MW
Alabama large-load contract review rules adopted Oct 6, 2026
FPL
Annual cluster; 45-day window each January, 150-day study
Retail customer under the LLCS tariffs
50 MW+ at 85% load factor
SB 484 compliance filing, Oct 1, 2026
Duke Energy (DEC/DEP)
Two-phase cluster; window each February, 90-day and 150-day phases
Duke technical rules, plus a proposed NC tariff
Above 40 kV, typically 50 MW+
Large-load technical rules (Rev. 001) effective Oct 15, 2026
APS
Annual cluster with a phased study and a flat $105,000 entry deposit
Retail customer under ACC rules; data-center queue closed
No posted process
Markets+ tariff filed Oct 14, 2026
PSCo
Annual cluster each March, plus resource solicitation clusters; 150-day studies
Retail customer under the proposed Schedule TL
50 MW+ (proposed)
Schedule TL hearing held Oct 21–28, 2026
PNM
Annual cluster; window each July, 150-day study
Retail customer under special contracts
No tariff yet
Base-case business practice effective Oct 16, 2026
PacifiCorp
One annual cluster for PACE and PACW; window each September, 150-day study
Retail customer of Pacific Power or Rocky Mountain Power
Above 20 MW (OR, WA, CA); 25 MW+ (UT, WY)
Business Practice #88 Rev 1.0 effective Oct 20, 2026

What the maps show

Each interconnection process guide shares the same layout. Here's how to use them.

  1. Maps switch: Swaps between the generator map and the large-load map. The diagram, the status strip and the project dials all change with it. Each page opens on the generator map, so switch here first if you're looking at a data center or other big load.

  2. Your project: Sliders for your project's size in MW and, on most generator maps, an estimate of network upgrade costs. Deposits, fees and security in the Costs tab recalculate as you move them. ERCOT has the size slider only. SPP swaps the upgrade estimate for an assumed GRID-C rate.

  3. Where things stand: Three short facts about the operator's process right now: open windows, pending filings, recent rule changes. They're the same facts shown in the summaries on this page.

  4. Legend: Shape tells you what a step is, and color tells you where a branch leads.

  5. Process map: Read it top to bottom along the vertical line, which is the main path from first application to a signed agreement or energized load. Branches to the right are exits, holds and side routes, labeled on the wire that leads to them. Each page suggests a good first click in the panel before you select anything.

  6. Detail panel: Select any box or diamond to open it. Three tabs cover What happens at that step, the Costs for a project your size, and Timing. Each ends with links to its sources.

  7. Sources: The tariffs, manuals, orders and summaries the page is built on. Check here for the date a rule took effect before relying on it.

How the interconnection queue process maps work legend

Who uses LandGate's interconnection maps

Whether you’re filing a project, siting a data center or vetting a deal, the maps show what stands between a project and the grid.

Substations Transmission Lines.png

Utilities, Consultants, and Regulators

Compare how other regions handle the same problem, such as large-load thresholds, deposit structures or fast-track options. The cross-region table and dated “latest rule change” entries show where each region stands as rules change.

Data centers.jpg

Data Centers and Large Load Siting

See how a 50 MW, 300 MW or 1 GW load connects in each region: who runs the study, which thresholds and tariffs apply, and where rules are still pending. Quickly rule out regions where the load process is closed, paused or still being written.

Solar Infrastructure.jpg

Renewable and Storage Developers

Plan a project’s path through the queue before you commit capital. See window dates, deposits due at each decision point, and withdrawal penalties, then compare costs across regions by adjusting your MW and upgrade estimate.

Retail Service Territory.jpg

Investors and Lenders

Conduct due diligence: Check what stage a project has reached, what it has paid in deposits, and what decisions and costs still lie ahead. A project past its final decision point carries very different risk than one still in its first study.

Know the rules. Now find the site.

See transmission lines, substations and interconnection activity for any parcel across all ISO's and RTO's in LandGate’s platform.