Duke Energy Interconnection: Find Power, Navigate the Queue, Secure Your Site

Duke Energy Carolinas and Duke Energy Progress run their own transmission system under one shared tariff, and the two combine into one utility on January 1, 2027. Explore DEP/DEC's interconnection process with our interactive step-by-step guide, then use LandGate’s capacity and parcel data to find the sites that can actually connect.

The map shows the process. LandGate shows how it plays out for your specific site.

Duke Energy Interconnection at a glance

Quick Facts
Duke Energy
Who runs it
DEC and DEP each plan and run their own transmission system under one shared FERC-approved tariff, and each runs its own queue. They combine into one utility on January 1, 2027. The North Carolina Utilities Commission and South Carolina PSC oversee state rules and retail rates.
Service areas
DEC: western and central North Carolina and upstate South Carolina. DEP: eastern and central North Carolina and northeastern South Carolina.
Generator study process
A two-phase cluster study. A 45-day window, filed through Duke’s PowerClerk portal, is followed by a 60-day engagement window, Phase 1 (90 days), Phase 2 (150 days, adding stability analysis), a restudy if needed, and a facilities study of 90 or 180 days.
Current cluster
The 2026 Phase 1 reports came out August 14, 2026. DEC has 11 requests totaling about 3,550 MW, mostly natural gas. DEP has 11 requests totaling about 500 MW, mostly storage.
Next window
Opens February 1, 2027. Duke hasn’t said whether it will run as one combined cluster or two.
Generator timeline
Roughly 20 to 23 months from window close to a signed interconnection agreement, plus about 5 months if a restudy is needed
Generator costs
A $5,000 non-refundable application fee and a study deposit of $150,000 to $250,000 for projects of 80 MW or more, plus a readiness deposit of twice the study deposit. The readiness deposit rises to 5%, 10% and 15% of network upgrade costs, and to 20% at the interconnection agreement.
Withdrawal penalties
None before the cluster study starts. After that, at least the study deposit, rising to 5% of upgrade costs after Phase 2, 10% during a restudy, 15% during the facilities study and 20% after signing if the plant never operates.
Large-load threshold
Duke’s large-load technical requirements cover loads connected above 40 kV, typically 50 MW or more, based on long-term projected demand
How large loads connect
Either through a wholesale customer, such as a co-op or town, which requests service from Duke with a 60-day System Impact Study and 60-day facilities study, or as a Duke retail customer
Large load security (wholesale path)
For requests of 100 MW or more, 100% of estimated facility and upgrade costs, as a letter of credit or cash
North Carolina large-load tariff
Decided November 16, 2026. The NCUC did not adopt the October 6 settlement - it created a data center schedule for loads above 50 MW, with a 15-year minimum contract above 100 MW and 75% minimum billing demand. The methods for assigning some transmission costs and a stranded-generation charge are still to be set.
Last updated
November 23, 2026

Duke Energy Generator Interconnection Process

Generator interconnection,
step-by-step

DEC and DEP study generators in a two-phase cluster, with one shared 45-day window that opens every February 1. Deposits rise at every decision point, from twice the study deposit at filing to 20% of network upgrade costs at the interconnection agreement.

​

  1. Check the queue and heatmap. DEC and DEP each post a queue and a heatmap of available capacity at each point of interconnection on their OASIS sites.

  2. Apply during the February window. Submit through Duke’s PowerClerk portal with proof of at least 90% site control, a $5,000 fee, a study deposit and a readiness deposit of twice the study deposit.

  3. Customer engagement window. Over 60 days, Duke holds a scoping meeting, and developers sign a Cluster Study Agreement.

  4. Phase 1 study. Duke studies the whole cluster over 90 days and assigns network upgrade costs. To continue, developers raise their readiness deposit to 5% of those costs within 20 days.

  5. Phase 2 study. Duke adds stability and short-circuit analysis over 150 days. To continue, developers raise their deposit to 10% of upgrade costs.

  6. Restudy and facilities study. Duke restudies the cluster if needed. Developers then show 100% site control and raise their deposit to 15%, and Duke designs the facilities over 90 or 180 days.

  7. Sign the interconnection agreement. Developers post a deposit totaling 20% of upgrade costs and sign the agreement, then construction begins.

Duke Energy generator deposits rise at each stage: two times the study deposit at filing, then 5%, 10% and 15% of network upgrade costs after Phase 1, after Phase 2 and at the facilities study, and 20% at the signed interconnection agreement.
Two ways to connect a large load with Duke Energy: as a Duke retail customer working with Duke directly, or through a co-op or town that requests service from Duke. Both paths must meet Duke’s large-load technical requirements.

Duke Energy Large Load Interconnection Process

Large Load interconnection,
step-by-step

Large loads in Duke's Carolinas territory connect one of two ways: as a Duke retail customer, working with Duke directly, or through a wholesale customer such as an electric co-op or town that takes network transmission service from Duke. Both paths must meet Duke's large load technical requirements for loads above 40 kV, typically 50 MW or more. Only the wholesale path runs through Duke's OASIS studies.

​

  1. Check Duke's technical requirements. Revision 001, effective October 15, 2026, covers protection, power factor, ride-through, modeling data, commissioning and monitoring. Smaller loads follow Duke's normal service rules.

  2. Choose who serves the load. Either Duke as a retail customer, or a wholesale customer such as a co-op or town.

  3. Retail path in North Carolina. Work with Duke directly. The NCUC's new data center schedule covers loads above 50 MW, with a minimum 15-year contract for facilities above 100 MW and minimum billing at 75% of contracted demand. gcn

  4. Wholesale path: pre-application and application. The wholesale customer can send an optional, non-binding pre-application that gives no queue priority, then applies to designate the new network load. Duke reviews it for completeness within 15 days.

  5. Studies. If Duke requires them, a System Impact Study and a Facilities Study each take about 60 days after their agreement is signed.

  6. Sign the service agreement and post security. The customer has 30 days. For requests of 100 MW or more, security covers 100% of estimated facility and upgrade costs, as a letter of credit or cash. Below 100 MW, security is needed only if those costs reach $10 million.

  7. Build and energize. Duke files the agreement with FERC, which takes about 60 days to accept it, builds the upgrades, and the load completes commissioning and ramps up.

Monthly interconnection queue outlook

Each month, LandGate tracks every change across U.S. interconnection queues: what changed, what withdrew, where scheduled slipped, and which application windows open next.

 

Get the free report to see where the grid can still take new projects.

What's changed recently in Duke Energy interconnection

Last updated November 2026

Duke is merging its two Carolinas utilities, tightening its rules for large loads and running its generator cluster under new financial readiness rules. If your project is in DEC’s or DEP’s territory, check which of these changes apply before the next window or agreement.

​

  • November 1, 2025: New financial readiness rules took effect for generator requests under the FERC, North Carolina and South Carolina procedures.

  • April 17, 2026: DEC and DEP first posted heatmaps of available capacity at each point of interconnection.

  • August 14, 2026: The 2026 Phase 1 reports came out: DEC with 11 requests totaling about 3,550 MW, mostly natural gas, and DEP with 11 requests totaling about 500 MW, mostly storage.

  • October 6, 2026: Duke, North Carolina’s Public Staff and large customers filed a settlement creating the state’s first large-load tariff, for loads of 50 MW or more at an 80% load factor, or any load of 150 MW or more.

  • October 15, 2026: An updated version of Duke’s large-load technical requirements took effect for loads connected above 40 kV.

  • November 16, 2026: The NCUC approved multi-year rate settlements for DEC and DEP, with new rates starting January 1, 2027. It did not approve the October 6 large-load settlement as filed and instead created its own data center schedule.

  • Coming up: DEC and DEP combining into one utility on January 1, 2027, with separate rates at first; New North Carolina rates taking effect January 1, 2027; The next cluster window opening February 1, 2027; Remaining decisions on how some transmission costs are assigned and how the stranded-generation charge is calculated.

How LandGate Helps with DEP/DEC Interconnection

Large loads have to choose between two connection paths and meet Duke’s technical requirements above 40 kV. LandGate brings the data behind those decisions into one platform.

Get your projects on the grid faster with reliable transmission data.

Pick a site before the February window

Duke accepts requests only from February 1 for 45 days, and applications need at least 90% site control. Search parcels by criteria such as distance to a substation and available offtake capacity, and see available transfer capacity at transmission-level injection points to find points of interconnection worth applying for.

Know your upgrade exposure

Duke’s deposits climb to 5%, 10%, 15% and then 20% of network upgrade costs as a project advances. LandGate’s automated offtake capacity studies show substation details, capacity results, limiting elements such as transmission lines and transformers, and queue information, so you can spot upgrade risks before committing capital.

Find the right substation & power

Duke’s large load requirements apply above 40 kV. Requests of >100 MW must post security for 100% of facility & upgrade costs. LandGate shows the subtransmission grid (typically between 34.5 kV and 138 kV) with hosting capacity and ATC at the line level. Its Data Center Due Diligence Reports rank the closest substations by capacity available to serve the site.

Lock down the best sites

Duke requires at least 90% site control at application and 100% at the facilities study. LandGate pairs its grid data with proprietary landowner leads, nationwide ownership data and contact info, and a map-based CRM to help you find, secure, and track the right parcels, including off-market properties with the right infrastructure profile.

Compare capacity across DEC and DEP territory before deposits climb at every decision point.