Large-Load Interconnection Reform: Five Operators Compared


As of late November 2026, five grid operators have asked FERC to approve five different ways to connect data centers. PJM would study load and generation together in one 12-month cycle, while MISO, ISO-NE and NYISO would offer non-firm service that wholesale price triggers can interrupt (POWER). For developers, the region now shapes timeline, cost and curtailment risk.
What Did FERC Order, and Where Do the Filings Stand?
On June 18, FERC issued show-cause orders to the six regional grid operators it oversees: PJM, MISO, SPP, CAISO, ISO-NE and NYISO. The orders asked each to justify its tariff or reform it across five areas: study processes (including alternative transmission technologies), cost-shift protections and cost transparency, co-location and behind-the-meter generation, new services for flexible large loads, and studies of generation serving nearby or co-located loads (FERC).
Rather than set one national standard, FERC directed each operator to develop rules suited to its own market. States keep authority over retail sales to large loads and over siting decisions and construction (Utility Dive).
Five of the responses were filed on Nov. 13 and 16. SPP, the sixth operator, filed its response ahead of its Nov. 20 deadline (RTO Insider). All of it remains subject to FERC review, and several of the largest reforms still need further tariff filings, stakeholder processes or software development before they take effect (POWER).
How Do the Five Operators' Plans Differ?
The plans converge on one idea, interim or non-firm service so a load can energize before every network upgrade is built, but they diverge on how that service is curtailed and who must bring capacity (POWER).
Operator | Early-connection option | What can interrupt non-firm service | How capacity is handled |
PJM | Firm and non-firm contract demand service; Interim NITS (energy-only) | Same curtailment priority as non-firm point-to-point service; no uniform price trigger | Firm service keeps capacity obligations; Interim NITS carries no generation capacity charges, per PJM's transmission owners |
MISO | GRITS (ongoing firm and non-firm mix); Interim NITS with optional firm step-up | Locational price above $100/MWh at the load's node, or a capacity advisory | Firm GRITS and Interim NITS keep capacity obligations; non-firm GRITS may be excluded |
ISO-NE | Firm, non-firm and interim contract demand service | Redispatch above $250/MWh | Firm service requires Bring Your Own New Capacity |
NYISO | Firm and non-firm withdrawal service | $200/MWh maximum bid price, plus operator curtailment when reliability requires it | Project-specific resource adequacy study; a co-located or partner resource can support firm rights |
CAISO | Flexible Interim Load Interconnection (FILI) | Project-specific limits: schedules, remedial action schemes or transmission owner curtailment | No customer-specific generation requirement; load-serving entity obligations continue |
Source: POWER, Nov. 19, 2026. All five proposals remain subject to FERC review.
Because these triggers reflect different market and reliability mechanisms, they are not directly comparable measures of how often a load would be curtailed. MISO said historical data suggest its $100/MWh threshold would permit service in more than 95% of hours, while ISO-NE said its $250/MWh price occurred in roughly 1% of hours from 2021 through 2025 (POWER).
SPP is the exception to the pattern of pending proposals, which is why it is not in the table. FERC approved its High Impact Large Load process in January 2026, and the rules took effect Jan. 15. In June, FERC approved SPP's Conditional High Impact Large Load Service (CHILLS), a non-firm service that lets a load connect for up to seven years while firm service is built (Utility Dive). CHILLS took effect July 1, and SPP's rules apply to loads of 50 MW or more above 69 kV, or 10 MW or more at 69 kV and below (LandGate).
Why Does Resource Adequacy Now Shape Site Feasibility?
Resource adequacy is where the plans split most sharply. ISO-NE would require large loads seeking firm service to designate sufficient new capacity, with interim service until those resources reach commercial operation. NYISO would let a load secure firm withdrawal rights through a co-located resource or a partner resource elsewhere in the same capacity region, each under a 15-year arrangement. CAISO argues no customer-specific generation requirement is needed because it has no centralized forward capacity market, though load-serving entities still carry procurement obligations (POWER).
The practical effect is that proximity to deliverable new generation, whether co-located or elsewhere in the same capacity region, can become part of a site's feasibility rather than a separate procurement exercise.
How Are Study Timelines and Cost Commitments Changing?
PJM's Fast Energization Process would fold generation and large-load studies into a single 12-month cycle, roughly half the length of its current cycle. NYISO estimates 18 months to two years for its process, while ISO-NE targets a system impact study within 90 days of the study agreement and MISO would run three study cycles per 365 days (POWER).
Speed comes with financial commitments. PJM's transmission owners propose recurring revenue commitments of 80% to 100% of the revenue tied to requested firm service, and MISO's proposal would size commitments to recover covered upgrades over 20 years. MISO would also charge a nonrefundable $250,000 application fee and a $100,000 study deposit (POWER).
These commitments respond to concern that existing customers could end up paying for data center-related infrastructure. ISO-NE would also post a list of the network upgrades identified for each large load, with cost estimates, on its website (Utility Dive).
What Changes for Co-Located, Behind-the-Meter and Flexible Power?
Behind-the-meter netting is a target of reform in at least three regions. PJM proposes to cap the daily demand reduction credited to retail behind-the-meter generation at 50 MW at a single electrical location, ISO-NE proposes a zero-megawatt netting threshold, and NYISO proposes to retire its behind-the-meter net generation model by May 1, 2029 (POWER).
Operating requirements are also rising. On July 22, 2026, nearly 3.9 GW of data center demand in PJM shifted from utility supply to onsite generation after a transmission disturbance. PJM now proposes ride-through requirements for loads of 50 MW or more with at least 25 MW served through power electronics, starting Jan. 16, 2027 if approved. For co-located designs, PJM would make customers responsible for the hardware and software that enforce authorized withdrawals, and an initial misoperation could suspend withdrawals for up to 120 days, with a second ending the agreement (POWER).
When Would These Changes Take Effect?
Outside SPP, most of this is not live yet. Proposed dates cluster in 2027 and 2028, and MISO's new service would not begin before 2029 (POWER).
SPP: High Impact Large Load process in effect since Jan. 15, 2026; CHILLS non-firm service in effect since July 1, 2026; new show-cause filings pending
NYISO: Large Load Integration Procedures proposed for Feb. 1, 2027
CAISO: most reforms requested for Feb. 16, 2027
PJM: most transmission service revisions on March 16, 2027, with the Fast Energization Process following in late November 2027
ISO-NE: new transmission services from June 1, 2028
MISO: GRITS not before Jan. 1, 2029
What This Means for Data Center Developers
These filings make the grid operator and the service class first-order screening variables, not afterthoughts. Five implications follow.
Underwrite curtailment at the node, not the region. Each non-firm trigger is tied to local pricing or constraints, so exposure depends on the pricing node, nearby transmission constraints and the service class a project can actually obtain.
Treat capacity as part of site control. Where operators ask loads to bring or designate new capacity, nearby deliverable generation, and the gas supply or other fuel access behind it, becomes part of what makes a site financeable.
Re-run behind-the-meter economics under the new rules. Designs that relied on generous netting, or on riding through disturbances by switching to backup power, face new costs and operating obligations.
Sequence entitlements with interconnection. FERC left siting to states, so a faster grid path does not help a project in a jurisdiction that has paused data center applications (Utility Dive).
Diligence by region and by date. Counsel quoted by Utility Dive noted that a term sheet signed against one region's tariff carries different risk than one signed against another's, because each filing lands on its own schedule (Utility Dive).
This is where site-level data matters. LandGate's data center layers include active data center locations, offtake (available power) capacity for grid-connected sites, and natural gas infrastructure for behind-the-meter power, which map to the questions above: where available power exists and where on-site generation could be supported.
LandGate also offers a data center moratorium layer that maps tracked moratoriums alongside power, land and infrastructure data, so entitlement risk can be screened in the same view as power.
Learn more by connecting with our team, energy@landgate.com or book a demo through the following button.
Frequently Asked Questions
Which grid operators did FERC order to act?
FERC directed six operators: PJM, MISO, SPP, CAISO, ISO-NE and NYISO (FERC). ERCOT is not among them. FERC also encouraged transmission owners outside RTOs to propose their own rules (Utility Dive).
What is non-firm transmission service for a data center?
It lets a large load withdraw power as available, with interruption under defined conditions, potentially before every network upgrade needed for firm service is complete (POWER). The interruption triggers differ by operator.
Do these changes apply yet?
Mostly not. The five operators' proposals remain subject to FERC review, and the earliest proposed effective dates fall in 2027 (POWER). SPP is the exception: its High Impact Large Load process and CHILLS non-firm service are already in effect (Utility Dive).
What size load do the new rules cover?
Definitions vary by proceeding, but the five November filings broadly appear to converge on a 50-MW threshold (POWER). SPP's in-force rules use 50 MW above 69 kV and 10 MW at 69 kV and below (LandGate).
Sources
Five Grid Operators Respond to FERC With Distinct Plans for Large-Load Integration, POWER, Nov. 19, 2026
Grid operators file closely watched large load interconnection reforms at FERC, Utility Dive, Nov. 17, 2026
6 takeaways from FERC's data center interconnection decision, Utility Dive, June 22, 2026
FERC launches aggressive, targeted action to speed large load integration, FERC, June 18, 2026
SPP Files FERC Show-cause Compliance Package on Large Loads, RTO Insider, Nov. 23, 2026
FERC approves SPP non-firm, large-load transmission service, Utility Dive, June 2026
SPP Interconnection Guide, LandGate, updated Nov. 23, 2026